|
|
|
AGM
Index
|
Arusha
Node Marie
Annual General Meeting 2005
15 April 2005
East
African Submarine Cable System (EASSy)
by E. Yonazi
-- East African Community Secretariat
|
Presentation
Outline:
1.
Project Background 
- Objectives
of the EASSy MoU Parties:
- Meet
Growing Demand for Broadband Connectivity in the region
- Seeking
quality and cost advantages of optic fibre connectivity
- Interconnect
with other similar cables will supplement existing, planned
terrestrial, satellite facilities
- Joint
Study and investment by the Parties for the Implementation
of such a system
- Social-Economic
Benefits:
- EASSy
will contribute towards the socio-economic development of
the region
- Improved
high capacity connectivity within Africa and with the rest
of the world.
- Improved
global connectivity to benefit all stakeholders
- Spur
terrestrial backbone links – improve cross-border connectivity
- EASSy Impact:
2.
Project Phases


Project Phases: Advanced Feasibility Development:
|
Current
agreed EASSy configuration will have a distance of about
9,900Km.
- The
Detailed Feasibility Study (DFS) by Axiom began mid-November
2004 (WB, DBSA).
- AXIOM
presented an interim report during the Rwanda meeting
|
Sites
survey in progress as part of the DFS by AXIOM:
- Mtunzini
– South Africa
- Maputo
– Mozambique
- Toliary
– Madagascar
- Dar-es-Salaam
– Tanzania
- Zanzibar
– Tanzania
- Mombasa
– Kenya
- Mogadishu
– Somalia
- Djibouti
– Djibouti
- Massawa
– Eritrea
- Port
Sudan
|
| System
scope should be anchored by end of April 2005 |
3.
Project Scope:Eastern Africa Submarine Cable system


Global
Connectivity

Strategic
Global Coverage:

4.
EASSy Project Participation Status:Current Membership

Current Position 16 Participants 13 Countries

EASSy
Project Participation Status: Potential members
-
At
least 8 other Countries Targeted
-
Mechanisms
in place to enable qualifying entities to join the project at
current and future stages (Accession Agreement)
-
Global
Carriers.: e.g. BT;France Telecom; Teleglobe; MCI
-
Development
Partners:
5.
Future Activities: Milestones

Activity
Finalize cable configuration
Issue invitation to tender
Financial Closing
Sign Supply Contract & C&MA
Cable Ready For Commercial Service |
Time
Frame
Q3 2005
Q3 2005
Q3 2005
Q3 2005
Q2 2007
|
6.
Capital Requirements

Project
cost is estimated to be US$ 200 million :
- Supply Contract
Costs
- Non-Contract
Costs
- Customs Duties
& Taxes
- Provision
for contingencies & other procurement
7.
EASSy Financing Indications and Ownership Structure

-
About
US$ 100m (50%) of required could be available from the MOU Parties
-
Hence
the need for other investors
-
Other
Possible sources of funding:
-
Operators
in the region that are not yet EASSy MoU parties
-
Global
carriers that may participate as equity partners
-
Debt-
development loans targeted
-
Ownership
structure to depend on the level of equity contribution from
potential users of the system (regional operators and global
carriers)
Options:
-
Club Structure- closed to only users of the system- preferred
if operators can raise all required investment
-
Private
company owning the system
-
Hybrid
(with elements of two above)- likely in form of a Special
Purpose Vehicle (SPV)
-
System
suppliers could be approached for possible project funding
8.
Key Project Risks and Responses

-
Inability
to raise required financing in time
-
Lack
of support of the project by key stakeholders
-
Lack of access to the cable by hinterland countries
-
Rapid
change in ICT and hence delays could lead to obsoleteness of
assumptions & Costs
-
Slow
communications policy harmonization across the countries
Responses:Establishment
of Backhaul (Interior)Links
-
MOU
Parties are collaborating in the planning and implementation
of backhaul links (Task Force established)
-
Planning
for alternatives routes for landlocked countries is a priority
to assure resilience
-
East
African Carrier Project & Others (eg.Comtel)

EASSy
Backhaul Routing Options:

East
African Backhaul Task Force- Routing Plan:

National
Fiber and Microwave Networks:

Conclusion:

-
EASSy
Project will, as in the case with SAT-3/WASC/SAFE, serve as
a shining example in demonstrating the ability of African and
Global telecommunications companies to work together in harmony
towards realizing an important step and building block in pursuit
of the development and improvement of African infrastructure
-
The
model of the implementation of the Project will likely be replicated
in other multi-national infrastructure projects.
-
Project
Secretariat
Simon A. Olawo
Telkom Kenya, Telposta Towers, 24th Floor, Kenyatta Av.
P.O Box 30301, GPO, Nairobi Kenya
TEL: +254 20 316167,
FAX: +254 20 310104,
E-mail: solawo@telkom.co.ke
|
|